.bk J05 .fl S826jW.j .fd daily journal for S826 .ei jW .ed S826 .rd S826 .ri jW -wk Eighteen assigned workmen reported. Eight detailed workmen from A20 reported. One workman (Abd'l Rahman) from J1 detailed. One workman (Thayer) from J6 detailed. Pickman Kamiran out sick. Kagharan excused at 0600 for illness. Majid excused at 0700 to attend to sick child. Reported back at 1000. -sf dL sick in bed at home. -dy gB assigned a project to excavate a walkway along the south face of revetment wall, f3, from J1 into the southeastern corner of J5. Its purpose is to emphasize that the wall spans several excavation units. -sy Markers m4322 and m4886 loosened and removed. hB took and processed relays for k101 that we were unable to measure. -sg As tomorrow is the last day of excavation, the following projects must be completed. First, mKB must analyze today's ceramic finds from k101, k102, and k103 to assure that we have sufficent data from them to determe the phase when parts of revetment wall, f3, and staircase, f21 were built. Then, we will cover and backfill these loci. Second, we must complete excavating the access stairway from J1 to J5 along the south face of revetment wall, f3. Third, we must complete the removal of volumetric material, f159, in k100 to enhance the sightline from the panorama into J1. Fourth we must complete excavation of volumetric material, f167, in k32 to enhance the sightline from the panorama into k22 so that wall, f41, can be seen. Fifth, we will continue to explore for the escarpment that should continue west from excavation unit J1 into J5 along the bottom stones which form the south face of revetment wall, f3.