.bk J05 .fl S825jW.j .fd daily journal and feature descriptions for S825 .fn features .ei jW .ed S825 .rd S825 .ri jW -wk Nineteen assigned workmen reported. Eight workmen detailed from A20 reported. One workman detailed from J1 reported. -sg gB and jW met to discuss the strategy to complete the assigned work in the last two field days, which begin tomorrow. First we will improve the sightline from the new panorama by expanding the trianular cut, f167, in k32 by an additional meter. Ali, Ramadan, Mizer and the crew from A20 will accomplish this task. Second, we will continue to excavate loci k101, k102, and k103 to obtain additional ceramic material that will help us to date when revetment wall, f3 and staricase, f21, were built. Abd'l Rahman will do this. Third, we will complete the excavation of the sloping section, f159, east to the boundary of J1. Masood and Majid will accomplish this task. Fourth, we will follow the escarpment, f167, to the west from the western border of J1. Huessein will do this. Fifth, we will cut a ramp to prepare a staircase that will lead visitors from J1 upward into J5. Amer and Kamiran will accomplish this task.