1998-7-5jW sixteen workmen have been assigned, consisting of large picks and support. [Input file: I706JLW.J / I706JLW.-J]
1998-7-7jW sixteen workmen have been assigned under the direction of Abdul Kareem. jW and jL are visiting the site periodically to monitor progress and inspect findings. [Input file: I707JLW.J / I707JLW.-J]
1998-7-8gB We have 17 workmen, and I have placed Abd el-Karim Hassan in a position of general supervision, short of calling him so outright. He is doing very well, and is to be credited with the finding of the sealings within such a type of excavation as we have had (heavy, if controlled). Also, the general appearance of the square during and after each cycle of excavation is impeccable. [Input file: I707GB.J / I707GB.-J]
1998-7-8jW sixteen workmen assigned under the supervision of Abdul Kareem. Soon after work began, Akmed Hassan excused from worksite for illness. [Input file: I708JLW.J / I708JLW.-J]
1998-7-11jW fifteen workmen under the direction of Abdul Kareem. jW and jL are on site full time to monitor progress and record data. [Input file: I711JLW.J / I711JLW.-J]
1998-7-12jW continuing to excavate with 16 workmen under the supervision of Abdul Kareem. jW and jL on site to monitor and evaluate. [Input file: I712JLW.J / I712JLW.-J]
1998-7-13jW again excavating with 16 workmen under the direction of Abdul Kareem. Suleman still not fully functional due to back injury of I712. jW and jL on scene full time to monitor progress. [Input file: I714JLW.J / I714JLW.-J]
1998-7-14jW six workmen under the direction of Abdul Kareem to engage in final cleanup and preparation for final photographs. [Input file: I714JLW.J / I714JLW.-J]