Strategy (projected or implemented) |
2010-08-07 |
cJC |
After k3 had been finished being excavated during the 2008 season gB wanted to cut back k3 by one meter from inside k200. As this was considered a cleaning operation of the trench no features were assigned. In the study season of 2010 it became necessary to refer to the brickfall and ash seen in this section and so feature numbers were assigned. These features were identified in section and have not been excavated. [Input: U807CJC.j] |